ERG's Bolashak chrome mine reaches first million tonnes after hydrogen halt
The Kazchrome mine in Aktobe region is designed for 7.5 million tonnes of ore a year; ERG is spending more than KZT 1 trillion to get it there.
Written with AI tools by Corridor Minerals' editorial system; the publisher is responsible for it. How this site works

Bolashak, the underground chrome ore mine at the Donskoy mining and processing plant in Kazakhstan's Aktobe region, has produced its first million tonnes of ore since its launch, Eurasian Resources Group (ERG) said in a statement on 30 September 2026.

ERG said it took less than two years to reach the mark, but the figure is small against what the mine is built for. Bolashak has a design capacity of 7.5 million tonnes of chrome ore a year, and ERG is investing more than KZT 1 trillion in building it and bringing it to that capacity, the statement says. A million tonnes in just under two years means an average of a little over half a million tonnes a year, well under a tenth of the design rate, on Headframe's arithmetic from those two figures. The statement does not give a current monthly rate or a date for reaching full capacity.
The mine belongs to TNC Kazchrome JSC, which ERG describes as part of the group; the statement gives no percentage holding. It matters beyond Khromtau because it feeds the group's ferroalloy smelters. ERG's page on Kazchrome says the Donskoy deposits are the main raw material base for ferroalloy production at the Aktobe and Aksu plants, and that Bolashak, launched at the end of 2024 as the second phase of the mine named after the 10th anniversary of Kazakhstan's independence, should allow the country to raise output to up to 2 million tonnes of ferroalloys a year.
A three-month stoppage
The ramp-up has not been smooth. Four months after the launch, work at the mine was suspended because hydrogen had appeared in the workings, the statement says. The mine team, Kazchrome specialists and outside research organisations spent three months on measures that allowed production to restart safely, the company said. It did not say how much ore was lost during the stoppage, where the gas came from or what the measures were.
Since May 2026, new sections of the mine have been worked by sublevel caving, a bulk underground method, with self-propelled equipment, the statement says. ERG said the mine had been equipped from the start with drill rigs capable of automatic drilling under remote control from the surface and with a fully automated hoist.
Yerzhan Abdulabekov, general director of Kazchrome, said the task now was to make each further million tonnes more stable, safer and more efficient, and that the company was changing the mining method, raising mechanisation and training staff, because the mine's output affected the reliability of the whole Kazchrome chain from the Donskoy plant to the ferroalloy smelters, the Russian-language statement says. Kudrat Shamiyev, chief executive of ERG in Kazakhstan, linked the mine's development to jobs and the long-term future of Khromtau, the company said. ERG also posted the news on its official Telegram channel on 1 October.
Faster than the older shafts
ERG compared the pace with the plant's earlier underground mines. About 40 years ago, the Molodezhnaya mine took four years to produce its first million tonnes, and the mine named after the 10th anniversary of independence took five years, the statement says. The comparison says nothing about ore grade or about how much of each mine's output went to the smelters.
For scale, ERG's Kazchrome page lists 4.828 million tonnes of ore mined in 2022, the latest year it shows, without a split by mine. On the same page the Aksu ferroalloy plant is described as producing more than 1 million tonnes of products a year and the Aktobe ferroalloy plant more than 700 thousand tonnes of ferroalloys a year. A further unit, Zhairem manganese operations, sends more than 100 thousand tonnes of manganese concentrate a year to Kazchrome's ferroalloy plants, the page says.
What the release does not say
- The chromium oxide grade of the ore mined at Bolashak, or the recovery at the concentrator.
- How much of the more than KZT 1 trillion budget has been spent, and how it is financed.
- A date for reaching the design capacity of 7.5 million tonnes a year, or an output target for 2026.
- Whether the hydrogen issue affects other parts of the deposit.
The company's figures for full-year 2026 output, which ERG has not yet scheduled, are the next document that would show whether the ramp-up has reached a steady rate.