Indian-backed Altyn-Tor gold plant starts test runs in Kyrgyzstan

First metal was planned for December 2024; investment had reached $34.2 million by August, above the $25 million minimum cited, and no capacity is given.

Written with AI tools by Corridor Minerals' editorial system; the publisher is responsible for it. How this site works

A town spread along a valley floor beneath bare brown mountains
Naryn, Kyrgyzstan, seen from the south, 2012 Photo: Pmelton87, CC BY-SA 4.0, via Wikimedia Commons, cropped

A gold processing plant developed by Avelum Partner at the Altyn-Tor section of the Solton-Sary deposit in Kyrgyzstan's Naryn region began test operations on 12 September, the Times of Central Asia reported on 14 September.

India's Deccan Gold Mines, which holds a controlling stake in Avelum Partner, describes the project as the first Indian investment in Kyrgyzstan's gold mining sector to reach this stage, the report says. The state-owned miner Kyrgyzaltyn holds the other part of the partnership.

Ownership and scope

Kyrgyzaltyn's own project page says the company and Avelum Partner signed a simple partnership agreement on 20 December 2021, with Kyrgyzaltyn holding 35 per cent and Avelum Partner 65 per cent. The agreement covers integrated development of the Altyn-Tor plot of the Solton-Sary deposit, and the work involves processing technogenic formations, meaning existing tailings storage facilities and mining waste dumps. The Times of Central Asia reports that, under the agreement, commercial-grade gold must be delivered to Kyrgyzaltyn and the Indian partner cannot export it independently. The page does not give the plant's capacity, the investment amount or job numbers.

The page of Altyn-Tor partnership with Avelum Partner (branch information) as published online
The document as published: Altyn-Tor partnership with Avelum Partner (branch information). Kyrgyzaltyn JSC, 17 October 2026.

Investment had reached $34.2 million by the end of August 2026, according to the same report. Kyrgyzaltyn said that at planned capacity the plant should create at least 400 jobs, more than 95 per cent of them for Kyrgyz citizens.

A later start than planned

The timetable has moved. When the plant's foundation was laid in July 2024, Kabar reported that the investment would be at least $25 million, with more than $8 million already spent, and that first commercial metal was planned for December 2024. Test operations in September 2026 therefore came about 21 months after that date, and the $34.2 million invested is about 37 per cent above the $25 million minimum cited in 2024, on simple division. Kabar's account gave the same job figures, at least 400 posts with more than 95 per cent for Kyrgyz citizens, and described the gold sources as the tailings dump, substandard overburden ore and open-pit reserves.

The deposit and its neighbours

Solton-Sary lies about 355 kilometres from Bishkek at an altitude of 3,500 to 3,600 metres. Kyrgyzaltyn's deposit page says the field has three areas, Buchuk, Ak-Tash and Altyn-Tor, with total probable gold reserves of about 20 tonnes. Test production began at Altyn-Tor in 1994. The open pit was placed on care and maintenance in 1997 because falling gold prices and low end-to-end recovery made it unviable, and mining resumed in early 2003 as prices and recovery improved. The existing gravity plant has a capacity of 100 thousand tonnes of ore a year and produces more than 100 kilograms of gold a year, the company says.

A second project operates next door. The Times of Central Asia reports that the Kyrgyz-Chinese company Zhong Ji Mining, which is developing the Buchuk section, launched a processing plant in test mode in October 2024 and produced 876.3 kilograms of gold in 2025. It cites explored reserves at Buchuk of about 12 tonnes and a possible further 22 tonnes of resources. The same report recalls that residents of the Naryn region protested against Zhong Ji Mining's operations in 2019, linking mining to livestock deaths and fearing contamination, and that the protest turned into clashes on 5 August 2019, after which authorities suspended operations.

The report also places the project against the wider sector. Kumtor, Kyrgyzstan's largest gold mine, was taken under state control from Centerra Gold in 2021, and a 2022 settlement transferred ownership to Kyrgyzaltyn. The capacity of the new Altyn-Tor plant is not given in the Kyrgyzaltyn page, the Kabar report or the Times of Central Asia report, so production figures from the test phase will be the first indication of its scale.

Sources

Assay notes

  1. Altyn-Tor partnership with Avelum Partner (branch information)Kyrgyzaltyn JSC, Primary source, 17 October 2026
  2. Solton-Sary / Altyn-Tor (branch information)Kyrgyzaltyn JSC, Primary source, 17 October 2026
  3. Indian Gold Mining Project in Kyrgyzstan Reaches Production StageThe Times of Central Asia, Secondary source, 14 September 2026
  4. Indian investors invest in construction of processing plant at Solton-Sary gold fieldKabar (Kyrgyz national news agency archive), Secondary source, 11 July 2024