MiningExplainer
KAZ Minerals' own mines could supply about 365,000 tonnes of copper a year
That is twice the 182,400 tonnes of copper in first-half concentrate; the Aktogay smelter is designed to make 300,000 tonnes of cathode a year.
Written with AI tools by Corridor Minerals' editorial system; the publisher is responsible for it. How this site works

KAZ Minerals Group is to build a copper smelter at Aktogay, in Kazakhstan's Abay region, designed to make 300,000 tonnes of cathode copper a year from its own concentrate, with first cathode scheduled for 2030, Trend News Agency reported on 20 October.
The report covered the ceremony at which President Kassym-Jomart Tokayev, joining by video link, launched the $1.8 billion project. KAZ Minerals' production reports show how much copper its mines now put into concentrate, and where it comes from.
China's NFC is the engineering partner, and the plant is expected to create more than 1,000 jobs and to produce metallic gold, silver and sulphuric acid as by-products, Trend reported, citing the presidential press service. Once the plant is commissioned, Kazakhstan will enter the world's top 10 producers of high-quality refined copper, Trend reported, and it quoted Tokayev as saying: "This will fully meet the needs of the domestic market." The report gives $1.8 billion as the project's value and says nothing about how it will be financed.
Where the copper would come from
KAZ Minerals produced 179,800 tonnes of copper in the six months to 30 June 2026, against 184,000 tonnes a year earlier, its production report of 11 August shows. That figure counts payable metal in concentrate plus cathode made from Aktogay's oxide ore, 5,700 tonnes in the half, which comes from ore sent to leach pads rather than through a concentrate. The copper contained in concentrate, which is what a smelter takes in, came to 182,400 tonnes across the group's four operations, on the Data Desk's addition of the report's figures.
| Operation, first half of 2026 | Copper grade processed | Copper in concentrate, tonnes | Copper production, tonnes | Gold production, ounces |
|---|---|---|---|---|
| Aktogay, open pit | 0.41% | 113,700 | 114,300 | 1,800 |
| Bozshakol, open pit | 0.37% | 46,800 | 44,700 | 37,200 |
| East Region, three underground mines | 1.90% | 19,100 | 18,100 | 6,200 |
| Bozymchak, Kyrgyzstan | 0.62% | 2,800 | 2,700 | 12,700 |
| Group | 182,400 (calculated) | 179,800 | 57,900 |
Source: KAZ Minerals production report for the six months to 30 June 2026. Copper and gold production are payable metal; Aktogay's copper production includes its oxide cathode. The group's copper in concentrate is the sum of the four operations.
The arithmetic against 300,000 tonnes
At the first-half rate, the group's operations would put about 365,000 tonnes of copper a year into concentrate, on simple doubling of the six-month total, against the plant's design output of 300,000 tonnes of cathode. Aktogay's concentrate alone would hold about 227,000 tonnes a year at the same rate, roughly three-quarters of that design output, so on these figures the plant would also need concentrate from Bozshakol or the East Region, or higher output at Aktogay. A smelter recovers less than all the copper it is fed, and neither Trend's report nor the production report gives a design recovery, so this compares contained copper with cathode capacity; it is not a feed plan.
Doubling also ignores variation between quarters: group copper production was 87,900 tonnes in the first quarter and 91,900 tonnes in the second, the report shows.
The two open pits processed ore grading 0.41 per cent copper at Aktogay and 0.37 per cent at Bozshakol in the first half, against 1.90 per cent at the East Region mines and 0.62 per cent at Bozymchak. Bozshakol accounted for most of the year-on-year fall in copper: its ore extraction dropped to 15.2 million tonnes from 18.2 million and its copper production to 44,700 tonnes from 47,600, a fall of 2,900 tonnes out of the group's 4,200. Aktogay's copper production was 114,300 tonnes against 114,800, and group gold production fell to 57,900 ounces from 62,600. The first-quarter report, published on 14 May, said output fell at Bozshakol in that quarter and that the mine experienced reduced throughput and recoveries as a result of changes in ore characteristics.
Where the concentrate goes now
The reports do not name buyers or smelters. They do show cathode already in the group's sales chain: first-half copper sales of 172,900 tonnes were 4 per cent below production, which the report attributes to shipment timing differences and increased volumes of cathodes in transit and smelter work in progress at the period end, and its definition of sales includes toll-processed metal. Kazakhstan already exports refined copper, as Corridor Minerals' analysis of refined copper shipments has shown; Trend's report says the new complex will process the group's own concentrate.
Trend's report puts the national picture at more than 9,500 deposits, about 160 million tonnes of ore mined and around 3.5 million tonnes of copper concentrate produced each year. KAZ Minerals reports copper content rather than concentrate tonnage, so its share of that concentrate cannot be calculated from its reports. The Aktogay plant is not the only new smelter in preparation: a separate project at Balkhash was reviewed by the prime minister in October.
Production figures are KAZ Minerals' own for the six months to 30 June 2026 and 2025, published on 11 August. The group's copper in concentrate, the annual rates and the shares of the design output are the Data Desk's calculations: a sum of the four operations, a simple doubling of six-month figures, and a division by 300,000 tonnes. The next document is the group's third-quarter production report; the first- and second-quarter reports appeared on 14 May and 11 August.
Sources