Aluminium of Kazakhstan readies Taunsor bauxite pits for first ore in 2028

Hearing documents set ceilings of up to 1.5m tonnes a year per section, though approved balance reserves total about 9.5m tonnes across the four areas.

Written with AI tools by Corridor Minerals' editorial system; the publisher is responsible for it. How this site works

A reddish brown lump of rock dotted with small round grains and holes, on a dark display surface
A sample of bauxite, the main ore of aluminium, on museum display, 2021 Photo: Koreller, CC BY-SA 4.0, via Wikimedia Commons, cropped

Aluminium of Kazakhstan JSC, ERG's alumina producer, is preparing to open the Taunsor bauxite deposit in Kostanay region's Kamysty district, with open-pit mining on the first two sections to start in 2028, the mining portal Qazba.kz reported on 30 September, citing public hearing documents.

The plans put section No. 19 at up to 1.5 million tonnes of ore a year and section No. 18, ore body 1, at up to 500 thousand tonnes a year, each for nine years.

The company is ERG's link between ore and metal. ERG's page on Aluminium of Kazakhstan describes it as the only alumina producer in Kazakhstan, making alumina from bauxite mined in Kostanay and Pavlodar regions at its Pavlodar plant. Mining at Taunsor will be carried out by its Krasnooktyabrsky bauxite mining branch, which works the Krasnooktyabrskoye deposit 70 to 90 km north of Taunsor, Qazba.kz reported.

The page of Aluminium of Kazakhstan JSC (enterprise page) as published online
The document as published: Aluminium of Kazakhstan JSC (enterprise page). Eurasian Resources Group, 30 September 2026.

The timing matters because ERG has said it wants to smelt all of its alumina at home. A planned second phase at Kazakhstan Aluminium Smelter, set out by an ERG executive in September, would add up to 400 thousand tonnes a year of metal capacity from 2028 or 2029, Kursiv has reported, and a larger smelter needs a secure long-term bauxite supply.

Five sections, staggered over a decade

The hearing documents cover preparatory work on five sections before open-pit mining begins: hydrogeological studies, haul roads and stripping of topsoil, Qazba.kz said. Preparation on sections 18 (ore body 1) and 19 is scheduled for 2026 and 2027, and on the other three sections from 2026 to 2031.

  • Section 18, ore body 1: from 2028, nine years, up to 500 thousand tonnes of ore a year.
  • Section 19: from 2028, nine years, up to 1.5 million tonnes a year.
  • Section 18, ore body 8: from 2031, nine years, up to 500 thousand tonnes a year.
  • Section 25: from 2035, 11 years, up to 500 thousand tonnes a year.
  • Section 20: from 2037, 10 years, up to 529 thousand tonnes a year.

The schedule is drawn from the Qazba.kz account of the published mining plans. No mining has previously taken place at Taunsor, and the nearest village, Druzhba, is 18 km away, the portal said.

The ceilings exceed the reserves

A 2016 protocol of the State Reserves Commission, cited in the plans, approved balance reserves on sections 18, 19, 20 and 25 at 9,528.8 thousand tonnes of bauxite, of which 9,510.4 thousand tonnes are in category C1 and 18.4 thousand tonnes in C2, with a further 2,915.7 thousand tonnes counted as off-balance, Qazba.kz reported. These are categories under the national classification inherited from the Soviet system, not reserves reported under an international code, and the report gives no bauxite grade.

Multiplying each section's maximum annual rate by its stated life gives about 33.3 million tonnes, more than three times the approved balance reserves, on Headframe's arithmetic from the five figures reported by Qazba.kz. The annual numbers are therefore permitted ceilings for each section, not a production plan. On approved reserves alone, the deposit would supply the combined maximum rate of 2 million tonnes a year from the first two sections for under five years.

Exploration at Taunsor dates from 1957, when the deposit was found, and 25 ore sections were prospected and explored up to 1985, the plans say. Aluminium of Kazakhstan signed an exploration contract with the government in 2005, but the programme was cut back to sections 18, 19, 20 and 25 because much of the deposit lies inside a nature reserve of the same name, the portal reported.

What the documents do not say

  • The alumina content and silica ratio of the Taunsor ore, which determine how it can be processed.
  • Output and remaining reserves at the Krasnooktyabrskoye deposit that Taunsor is meant to supplement.
  • The capital cost of the new pits.

The next step is completion of preparatory work on the first two sections, scheduled for 2027, ahead of first ore in 2028.

Sources

Assay notes

  1. «Алюминий Казахстана» начнет подготовку к освоению Таунсорского месторожденияQazba.kz, Secondary source, 30 September 2026
  2. Aluminium of Kazakhstan JSC (enterprise page)Eurasian Resources Group, Primary source, 30 September 2026
  3. ERG построит алюминиевый завод полного цикла за почти $1 млрд до 2029 годаKursiv, Secondary source, 25 September 2026