Energy TransitionBrief
Uzbekistan's 500 MW Forish solar plant generated 897m kWh this year
The ministry gives 897 million kWh against 1.1 billion kWh of yearly capability, 81.5 per cent by Data Desk arithmetic, a load factor near 25 per cent.
Written with AI tools by Corridor Minerals' editorial system; the publisher is responsible for it. How this site works

Uzbekistan's energy ministry said the 500 MW Forish solar plant in Jizzakh region has generated 897 million kWh since the start of this year, in a Telegram post on 24 October.

The same post says the plant can produce 1.1 billion kWh a year.
The post gives no end date for the 897 million kWh beyond "since the beginning of the current year". The figure is therefore not a full-year result. It also says the output saved 239.2 million cubic metres of natural gas and avoided 515.8 thousand tonnes of emissions, and equals the average electricity use of 448.5 thousand households over 10 months.
The two figures in the post can be set against each other. Output of 897 million kWh is 81.5 per cent of the 1.1 billion kWh annual capability. If the period runs to the day of the post, 24 October, it covers 297 days of the year, or about 81.4 per cent of the 365. That is the Data Desk's arithmetic, not a ministry figure, and it assumes the period ended on the post date.
On that assumption, the Data Desk calculates a capacity factor, the share of the plant's maximum possible output that it actually delivered, of about 25.2 per cent. The calculation divides 897 million kWh by 500 MW running for 7,128 hours (297 days). The design figure gives almost the same answer: 1.1 billion kWh over the 4,380 million kWh a 500 MW plant would produce in 8,760 hours is about 25.1 per cent. As yield, that is about 1,794 kWh per installed kilowatt against a design level of 2,200.
The design figure is not new. Trend reported in April 2024, citing the president's office, that the plant would cost $350 million and produce 1.1 billion kWh of green energy a year, with the first 200 MW due on the grid later that year. A June 2025 article on the Chinese state asset regulator's website describes a CHD Jizzakh 500 MW solar project that would supply over 1.1 billion kWh a year once operational. The sources differ on the developer: Trend names China Poly Group and China Electric, while the regulator's article refers to CHD, and the ministry post names none.
Three limits apply to the test. The post does not say when the whole 500 MW entered service, so any capacity connected part-way through the period would make the calculated factor look lower than the plant's true performance. It does not say whether 500 MW is the alternating-current or the panel rating, which changes the denominator. And the straight-line comparison ignores seasonality: the months the figure leaves out fall in the colder part of the year, when solar output is typically lower, so a full-year total would not simply continue at the same daily rate.
Within those limits, output to date sits close to the stated design level for the part of the year elapsed. It is a ministry statement, not a metered series, and the post gives no monthly data. For other recent Uzbek power projects, see Corridor Minerals' reports on the 300 MW wind plant in Karakalpakstan and the battery storage project in Bukhara.