Kazakhstan plans 13.3 GW of new power capacity by 2029
Renewables supplied 8.5 per cent of output in nine months against a 7 per cent target, and the plan aims for a 20 per cent capacity surplus.
Written with AI tools by Corridor Minerals' editorial system; the publisher is responsible for it. How this site works

Kazakhstan plans to commission 13.3 GW of new generating capacity through 2029, including 5.9 GW of renewables, Vice Minister of Energy Bakytzhan Ilyasov told a government meeting, the government said on 29 October.
The plan splits into 7.4 GW of base generation and 5.9 GW of renewable capacity. Ilyasov said it would cover the whole demand of the economy and the population, including energy-intensive artificial intelligence infrastructure and large data centres, and would create a 20 per cent surplus of generating capacity. The government's published account of the meeting gives no yearly schedule and no project list for the 13.3 GW.
Where the system stands
The grid now has 254 power sources, 172 of them renewable, with a combined capacity of 27.1 GW. Coal plants make up 13.7 GW, gas plants 7.1 GW and large hydropower stations 2.5 GW. Together those three come to 23.3 GW of the 27.1 GW, on a Corridor Minerals calculation, and the account does not break down the remainder.
Generation last year reached 123.1 billion kWh, which the account describes as a historical maximum, against consumption of 124.6 billion kWh. On Newsdesk's arithmetic, consumption was 1.5 billion kWh higher than generation. The account does not say how the difference was met.
Renewables supplied 8.5 per cent of total generation in the first nine months of 2026, against a target of 7 per cent, the account said.
Coal, solar and what is contracted
On renewables, the account says work is under way on auction tenders and on large solar initiatives, including a 300 MW China Energy plant and Tumar Commerce projects of up to 1 GW. It does not call either contracted, auctioned or financed, and it gives no dates. At least 8.4 GW of new renewable capacity is expected by the end of 2035, about 1.8 GW of it solar. Small distributed generation for businesses has grown fivefold since 2024 after legislative incentives, the account said.
A separate national project for coal generation covers 19 investment projects of about 7.8 GW: eight new plants of 5.3 GW and 11 expansion and modernisation projects of 2.5 GW. The account names Ekibastuz GRES-3, a thermal plant in Kurchatov and three combined heat and power plants in Kokshetau, Semey and Ust-Kamenogorsk. It does not say whether these projects fall inside the 7.4 GW of base generation.
Nor does it say which projects make up the 5.9 GW of renewables. Corridor Minerals reported 2.45 GW of Chinese wind agreements signed in September, including a 1 GW wind farm tied to an aluminium smelter, but the government's statement does not mention them.
What has been built so far
Official commissioning statistics for January to September 2026, published on 23 October, list the power facilities put into operation. Wind plants account for 250 MW, in Aktobe region (150 MW) and Karaganda region (100 MW). Solar plants add 95.8 MW, in Kostanay region (25.8 MW) and Mangystau region (70 MW). The tables also show 34.8 MW of hydropower in Zhetisu, 30.7 MW of gas turbines in Zhetisu and 22 MW of thermal capacity in Astana.
Those five lines add up to 433.3 MW, on a Corridor Minerals calculation. The tables mark some power entries as confidential, so the sum is not a full count, and the nine-month period is not the same as the plan's horizon.
The Eurasian Development Bank (EDB) added a regional caution in a report published on 29 October. It reported that installed capacity and available capacity differ: at the annual peak on 10 December 2024, about 6.6 GW of plant in the Central Asian Unified Power System was unavailable, because of cold reserve capacity, water and fuel limits, equipment condition and network constraints. The bank also put regional demand growth at up to 6 per cent a year, reaching around 370 billion kWh by 2030. These are regional figures, not Kazakhstan's alone.
The government statement names no industrial customers and does not mention metals producers. One metals project shows the gap: ERG's proposed second phase at its Pavlodar aluminium smelter, up to 400,000 tonnes a year, was announced without a named power source for the new potlines, as Corridor Minerals reported. Which of the new plants would supply such loads is not stated in the government's account.