Uzbek grid nearly doubles transformer power at 10 Tashkent substations
New transformers add 333.2 MVA before winter, with Qorasuv up from 53.6 to 138.6 MVA, as output on 29 October ran 15.9 per cent above a year earlier.
Written with AI tools by Corridor Minerals' editorial system; the publisher is responsible for it. How this site works

National Electric Grid of Uzbekistan has replaced power transformers at 10 substations in Tashkent, raising their combined capacity from 366.6 MVA to 699.8 MVA ahead of the autumn and winter season, the energy ministry said on 28 October.
The work adds 333.2 MVA of transformer capacity in the capital, the post says. Its stated aims are to raise the load the networks can carry, reduce the risk of supply interruptions and give households and businesses stable electricity. MVA measures the apparent power a transformer can pass, not the output of a power plant.
The largest single change is at the Qorasuv substation, where capacity rose from 53.6 MVA to 138.6 MVA, an increase of 85 MVA. Istiqbol went from 80 MVA to 126 MVA and Bibliotechnaya from 53.2 MVA to 90 MVA. Yangi Tuzel grew almost fourfold, from 12.6 MVA to 50 MVA, the steepest rise in proportion.
Five of the 10 substations now have 50 MVA: Saziit, up from 20 MVA, Risovaya from 32 MVA, Yangi Tuzel, Charogon from 26 MVA and Gornaya from 30 MVA. Vistavochnaya rose from 50 MVA to 80 MVA and Tuzel from 10 MVA to 16 MVA, the smallest of the 10.
The station figures in the post add up to 367.4 MVA before and 700.6 MVA after, 0.8 MVA more than each of the stated totals, on the Data Desk's addition. The difference between the two sums, 333.2 MVA, matches the stated addition; the post does not explain the 0.8 MVA gap between the station figures and its totals.
The upgrade comes as output rises. Uzbekistan generated 255.5 million kWh of electricity on 29 October, 35 million kWh or 15.9 per cent more than on the same day of 2025, the ministry's daily figure shows. The post's breakdown by type of plant adds up to 267.8 million kWh, 12.3 million kWh more than the stated total, and the post does not reconcile the two.
The same grid company is the counterpart in a wider programme. The Asian Development Bank's US$200 million loan, signed in October, will upgrade 60 critical distribution substations across Uzbekistan and strengthen the operational capabilities of JSC National Electric Grid of Uzbekistan; the bank says aging infrastructure, electricity losses and overloaded equipment have made reliable service harder, as Corridor Minerals reported. The ministry's post does not say how the Tashkent work was financed or whether any of the 10 substations is part of that programme.
Network capacity and generating capacity are separate constraints. At the annual peak load on 10 December 2024, plants in the Central Asian Unified Power System had 36.4 GW installed but only 28.8 GW available, the Eurasian Development Bank said on 29 October, a gap Corridor Minerals explained this week. Larger transformers let a substation take more load, but they do not add electricity to the system.
For industrial users in and around the capital, the post gives the transformer capacity now installed at each named substation, one measure of the load those nodes can take; it does not say how much new connected load the upgrade allows.
Sources
Assay notes
- Capacity of 10 substations in the capital increased, 333.2 MVA of additional capacity (in Uzbek)
- Number of the day: electricity generated on 29 October 2026
- ADB, Uzbekistan Sign $200 Million Power Modernization Loan
- EDB Proposes a Framework for Power Connectivity in Central Asia: Better System Management, Not Just More Power Lines