Critical Minerals

Sarytogan study puts Kazakh graphite mine capex at US$80.5 million

The upstream study estimates 50,000 tonnes a year of concentrate; Sarytogan held A$1.0 million at 30 September and lists financing talks as a next step.

Written with AI tools by Corridor Minerals' editorial system; the publisher is responsible for it. How this site works

Cover card: Kazakh graphite, Graphite study puts capex at US$80.5m

Sarytogan Graphite said its definitive feasibility study for the upstream Sarytogan graphite project in the Karaganda region puts total capital cost at US$80.5 million for 50,000 tonnes a year of graphite concentrate, in its quarterly report dated 26 October.

Planned annual sales of graphite concentrate in the upstream studytonnes per year
Source: Sarytogan Graphite, Quarterly Activities Report, 26 October 2026

The ASX-listed company published the study on 21 October, after the quarter ended on 30 September, and the report restates its headline figures. All of them are study estimates, not operating results: a pre-tax net present value at an 8 per cent discount rate (NPV8) of US$132.7 million, or A$189.6 million at a rate of US$0.70 to the Australian dollar, an internal rate of return of 19.8 per cent and an EBITDA margin of 51 per cent. The model assumes an average selling price of US$805 per tonne of concentrate against a total operating cost of US$364 per tonne.

What the study counts as ore

The study rests on an ore reserve estimate of 14.5 million tonnes at 29.1 per cent total graphitic carbon (TGC), made up of 2.5 million tonnes Proved and 12.0 million tonnes Probable, the report says. A higher-grade part of the reserve is 8.9 million tonnes at 31.8 per cent TGC. The mine plan schedules 8.5 million tonnes of that higher-grade ore over a nominal mine life of more than 50 years, which the company says uses less than 4 per cent of its 225 million tonne mineral resource at 29.2 per cent TGC. Reserve and resource figures are estimates prepared under the JORC Code, the Australasian reporting standard.

The deposit lies in the Karaganda region, 190 kilometres by highway from the city of Karaganda. The study plans 50,000 tonnes a year of concentrate at 90 per cent LOI1000 grade from a plant that has not been built.

Three markets for the concentrate

The report splits planned sales three ways. Of the 50,000 tonnes a year, 20,000 tonnes would be classified into three particle sizes for drilling fluids, lubricants and friction products, and 10,000 tonnes would go unclassified to foundries and iron recarburiser buyers. The remaining 20,000 tonnes would feed Sarytogan's own planned downstream business, which would make ultra-high purity fines and coated spherical purified graphite for advanced batteries.

The downstream project is not part of the US$80.5 million. The report cites the 2024 pre-feasibility study, which estimated an incremental pre-tax NPV8 of US$367 million (A$524 million) for an additional US$194 million of capital. A feasibility study for that downstream stage has still to start.

Sample work continues. The company said it has engaged dozens of potential offtake customers, including automakers, cell makers, anode manufacturers, alkaline battery companies, steel mills, foundries and brake makers, and that their identities are protected by confidentiality agreements. Samples of the unclassified concentrate are with potential recarburiser customers in Europe and Türkiye, and the fines are being prepared for a second round of tests with alkaline battery companies in the United States. The report names no signed offtake agreement.

The battery-grade side moved too. Corridor Minerals reported on 28 October that Sarytogan was sending 5 kilograms of coated spherical purified graphite to Europe for pouch-cell tests, after US trials gave grades above 99.99 per cent carbon. That plan came from the company's 14 September announcement. The quarterly report, dated 26 October, says the 5 kilograms has been shipped to a battery prototype demonstration organisation in Europe, for 5 ampere-hour pouch cells, and gives no cell results yet.

Cash, financing and next steps

Cash at the end of September was A$1,015,000, the report states, down from A$2,165,000 at the start of the quarter. The statement shows A$854,000 spent on exploration and evaluation and A$296,000 of operating outflow in the three months. The report does not say how the US$80.5 million would be raised.

The company lists its next steps as continued product testing and customer qualification, offtake and project financing discussions, a feasibility study on the downstream project, detailed design of priority infrastructure and an environmental and social impact assessment (ESIA) for international banks. The European Bank for Reconstruction and Development took a 17.36 per cent stake in Sarytogan in August 2024 for AUD 5 million (€3 million), the bank said, to fund a development programme that included preparing a feasibility study.

The company also describes the project as designated a Strategic Project under the European Union's Critical Raw Materials Act, a status Corridor Minerals traced in its look at EU partnership money in Kazakhstan. The report adds that the company finished three diamond holes, 1,000 metres in all, at the Ilksan copper prospect in its Baynazar project, and that follow-up drilling is needed to the west and south.

Sources

Assay notes

  1. Quarterly Activities Report, quarter ending 30 September 2026Sarytogan Graphite (ASX announcement), Primary source, 26 October 2026
  2. EBRD acquires stake in Sarytogan Graphite LimitedEuropean Bank for Reconstruction and Development, Primary source, 9 August 2024
  3. Downstream High-Quality CSPGSarytogan Graphite (ASX announcement), Primary source, 14 September 2026