KEGOC to add 440 MW to southern transit as Kazakhstan targets surplus
The grid operator plans a 500 MW link for western Kazakhstan by December 2027 and expects digital dispatch to save 5.5 billion tenge a year.
Written with AI tools by Corridor Minerals' editorial system; the publisher is responsible for it. How this site works

KEGOC, Kazakhstan's grid operator, will add 440 MW of throughput to the transit linking Almaty, Zhambyl and Shymkent by July 2027, its chairman Nabi Aitzhanov told a meeting chaired by Prime Minister Olzhas Bektenov, the government said on 5 November.
The meeting reviewed power projects of the Samruk-Kazyna sovereign fund. Bektenov cited President Kassym-Jomart Tokayev's declaration of 2027 as the Year of Large-Scale Nationwide Construction and said a sustainable energy surplus by 2029 requires generation, grids and the growth in consumption to move in step. He instructed officials to speed up development of the national electrical grid, told the Ministry of Energy to complete its update of the energy balance by September 2027 and ordered tighter oversight of investment projects in the power sector, the government said.
Aitzhanov said the project to unite the grid of western Kazakhstan with the Unified Power System will raise throughput to 500 MW, with completion in December 2027. A second stage, due in 2035, will close the high-voltage ring. KEGOC also plans upgrades to the Almaty and Zhetysu grids to take power from hydropower plants and new renewable facilities. The Energy Ministry first set out the western link in March as more than 600 km of new 500 kV line, The Astana Times reported.
Aitzhanov gave a fuller outlook to a committee of the National Kurultai, Trend reported on 3 November. KEGOC expects average annual load growth of 5.6 per cent in 2027 to 2033 and a capacity surplus of 2.8 GW by 2029, including the required reserve, and 5.9 GW by 2035 if the planned generation projects are built. Its investment programme rises from 48.8 billion tenge in 2024 to 181.8 billion tenge in 2026, the agency reported.
KEGOC expects digital technologies and artificial intelligence to yield 5.5 billion tenge a year, about 3 per cent of its EBITDA, through optimised power flows and lower losses. Connecting power plants to automatic frequency and active power control should save about 4 billion tenge a year. The National Dispatch Centre controls all 83 KEGOC substations and tracks more than 50,000 indicators, the government said.
Since the start of the year the North to South line has seen more than 70 sharp load surges, and 95 per cent of them were resolved without cutting power to households. The AI-KEGOC platform forecasts generation and consumption a day ahead across 21 power hubs and 169 renewable facilities, and synchrophasor monitoring raised the throughput of the North to South link by 250 MW without new construction.
Samruk-Energy chairman Ansar Aidarov, appointed at the end of October, reported progress on the modernisation of Almaty CHP-2, the reconstruction of Almaty CHP-3, combined heat and power plants in Kokshetau and Semey, the expansion of Ekibastuz GRES-2, combined cycle plants in the Kyzylorda and Turkestan regions, and renewable projects with energy storage and hydropower. The projects form part of the government's plan for 13.3 GW of new capacity by 2029, set out in October.