Aspire raises US$9.6 million in Mongolian OTC bonds to build Ovoot coking coal mine
The first five tranches pay 11% to 13%, and the company's cost model assumes about US$126 million of such bonds to reach first coal in late 2027.
Written with AI tools by Corridor Minerals' editorial system; the publisher is responsible for it. How this site works

Aspire Mining's Mongolian subsidiary, Khurgatai Khairkhan LLC, has raised US$9.56 million from a US dollar bond sold on Mongolia's regulated over-the-counter market to fund the Ovoot coking coal project in Khuvsgul aimag, the ASX-listed company said on 11 September. Five tranches had been issued by 9 September, with fixed coupons of 11.0 to 13.0 per cent a year and terms of 12 to 36 months, under a programme of up to US$60.0 million.

The bond is the first step in a staged financing plan set out in a reserve update released the same day. Its project cost model assumes that Khurgatai Khairkhan raises about US$126.0 million through OTC bonds in several tranches, at an assumed coupon of 12 per cent paid quarterly, 24-month terms and broker success fees of about 3 per cent. The model also includes about US$42.0 million of deferred payments to the Chinese contractor CCTEG-IEC, a vendor-financing structure supported by China Export and Credit Insurance Corporation (Sinosure) for 60 per cent of the contract price.
Who stands behind the bonds
Obligations under the current programme are guaranteed separately by Tserenpuntsag Tsedendamba, Aspire's largest shareholder with about 52.47 per cent of its shares, and by Gemnet LLC, which he founded, the bond announcement says. The guarantees cover principal, interest and certain ancillary amounts, and no guarantee fee is payable. Aspire cautions that the guarantees depend on the guarantors' financial position at the time and should not be regarded as an assurance that principal or interest will be paid in full or on time. Tenger Capital Securities is the underwriter.
The Mongolian Association of Securities Dealers approved registration of the programme on 27 July, and the Bank of Mongolia gave permission on 6 August for the issue, subscriptions and coupons to be settled in US dollars, according to the announcement. The bonds are offered only to professional investors in Mongolia. Aspire is considering a second programme of up to US$60.0 million, which would take possible issuance to US$120.0 million, depending on placement, market conditions and how far advance coal sales or offtake prepayments replace bond funding.
A smaller start on the same reserve
The reserve estimate, prepared by Glogex Consulting and effective 31 March 2026, reconfirms total coal reserves of 130.1 million tonnes, of which 76.8 million tonnes are proved and 53.3 million tonnes probable, and a marketable reserve of 97.9 million tonnes, unchanged from November 2024. The resource is 219.4 million tonnes. Ovoot is planned to produce a washed "fat" coking coal at 9.0 per cent ash for customers in China.
What has changed is how capital is spent. Phase 1 pre-production capital expenditure is now forecast at about US$61.2 million from 2026 to first scheduled coal, excluding about US$24.6 million of working capital and capital expenditure incurred to the end of 2025, the update says. The previous study put capital expenditure to first revenue at US$214.8 million, with about US$220 million of funding needed before revenue, although the company says the figures are not directly comparable. The difference comes from renting the mining fleet for the first three years, contracting road haulage for the first five, deferring non-critical site infrastructure and pricing in the US$69.9 million lump-sum contract with CCTEG-IEC, signed in December 2025, for the coal preparation plant and the coal handling facilities at the Erdenet rail terminal.
Using a long-term coking coal price of US$230 a tonne delivered at Erlian, China, in real terms, and a 10 per cent real post-tax discount rate, the model gives a post-tax net present value of US$1,483.3 million and a real post-tax internal rate of return of about 60 per cent. It assumes production starts in the fourth quarter of 2027 at about 1.5 million tonnes a year of run-of-mine coal, rising to about 2.5 million tonnes and then to a maximum of about 5.0 million tonnes over a mine life of about 31 years. About 12 per cent of the production target rests on inferred resources, which are not part of the reserve.
Road, rail and permits still open
Coal would be trucked from Ovoot to the Erdenet rail terminal and carried across the Trans-Mongolian railway to the Chinese border. The estimate assumes the Murun-Uliastai highway is built under a public-private partnership with the project paying a toll, and that enough rail capacity will be available, the update shows. The award of the road partnership agreement, environmental approval for the rail terminal and a statutory feasibility study and environmental assessment for a transport hub are still to be secured. Aspire lists rail capacity, a power connection and water supply among the principal outstanding dependencies.
The company also states that the financing amounts and timing in its cost model are modelling assumptions and do not constitute an assurance that funding will be obtained on those terms, and that the mix may change if advance coal sales or other sources replace bonds, the bond announcement adds.