AltynGold orders new mills at Sekisovskoye and moves Teren-Sai towards production

The Kazakh gold miner posted record first-half profit of US$42.7 million and won a contract extension at Teren-Sai; a 2.0 to 2.5 Mtpa expansion is still under review.

Written with AI tools by Corridor Minerals' editorial system; the publisher is responsible for it. How this site works

A gold processing plant with steel frames, mills and conveyors on red earth under a blue sky
The processing plant of the Sunrise Dam gold mine, Western Australia, 2010 Photo: Calistemon, CC BY-SA 4.0, via Wikimedia Commons, cropped

AltynGold, the London-listed gold producer operating in Kazakhstan, has ordered new crushing and milling equipment for its Sekisovskoye plant and moved its second asset, Teren-Sai, a step closer to production, after reporting the highest half-year earnings in its history, according to its interim results published on 29 September.

The page of Unaudited Interim Results, six months to 30 June 2026 as published online
The document as published: Unaudited Interim Results, six months to 30 June 2026. AltynGold (via Investegate), 29 September 2026.

The Kazakh industry ministry's working group approved a further extension of the Teren-Sai subsoil use contract after the end of June, and the company will apply within it to move to the production stage, the results say. It expects to update shareholders during the fourth quarter and will publish a separate announcement on the Teren-Sai mineral resource estimate. Chairman Kanat Assaubayev called the extension "an important step towards unlocking the value of our second asset".

Sekisovskoye expansion still under review

At Sekisovskoye, technical work has identified the potential to raise the existing plant's capacity by about 200,000 tonnes a year, and the new equipment has been ordered, the chairman's statement says. A broader increase to 2.0 to 2.5 million tonnes a year is still being reviewed; no investment decision has been made and the company expects to give an update by the end of 2026. Tailings dams 2 and 3 are being expanded to provide the storage needed for higher throughput.

The plant ran at its nameplate capacity of 1 million tonnes a year throughout the first half. Ore processed rose 10.1 per cent to 498,331 tonnes and ore mined 1.7 per cent to 458,201 tonnes. After bridging work between the main ore bodies was completed in April, the mined grade rose from 1.73 grams per tonne in the first quarter to 1.88 grams in the second, and the processed grade from 1.68 to 1.84 grams. Exploration drilling rose 38.8 per cent to 12,151 metres and 330 metres of capital development was completed on the two transport declines.

Record results, higher costs

Revenue rose 64.6 per cent to US$115.2 million and profit after tax 58.4 per cent to US$42.7 million, with adjusted EBITDA up 55.4 per cent at US$68.5 million, the results show. Gold sold rose 9.0 per cent to 24,628 ounces at an average realised price of US$4,615 an ounce, against US$3,071 a year earlier. Earnings per share were 156.38 US cents.

All-in sustaining costs rose to US$1,995 an ounce from US$1,530 for 2025. The company said more than half of the increase in cost of sales reflected the mineral extraction tax, which rises with the value of the gold produced, non-cash depreciation from its investment programme and higher volumes, with the stronger tenge and the timing of inventory movements adding to it.

Capital expenditure more than doubled to US$26.1 million from US$11.7 million, of which US$20.1 million was growth and one-off development spending on crushing and milling capacity, mining and transport equipment, underground development and tailings infrastructure. Cash generated from operations rose 64.7 per cent to US$52.1 million and net cash from operating activities, after US$15.6 million of tax payments, 19.7 per cent to US$36.5 million. Total borrowings fell by US$9.8 million to US$31.4 million, net debt was broadly unchanged at US$19.3 million and net debt to trailing adjusted EBITDA improved to about 0.15 times, according to the report. Net finance cost fell to US$0.2 million from US$2.4 million, and net assets rose 35.3 per cent to US$203.1 million.

The company kept its full-year production guidance of 52,000 to 55,000 ounces. First-half sales of 24,628 ounces imply a stronger second half to reach that range, which the chief executive, Aidar Assaubayev, linked to the higher grades achieved since April. The interim results give no capital cost for the larger Sekisovskoye expansion or for bringing Teren-Sai into production, and do not say how either would be financed.