Uzbekistan signs $4.7bn of power deals and plans second and third nuclear plants
Six projects add 3,000 MW of generation and 400 MW of storage; the president tied new reactors to rising uranium output but gave no sites, sizes or partners.
Written with AI tools by Corridor Minerals' editorial system; the publisher is responsible for it. How this site works

Uzbekistan signed agreements for six power projects worth a combined $4.7 billion on 16 October, adding 3,000 megawatts of generating capacity and 400 megawatts of energy storage, according to the presidential press service. The agreements were signed during an open dialogue between President Shavkat Mirziyoyev and investors in the fuel and energy sector. The release did not name the projects, their sponsors or their locations.

At the same meeting Mirziyoyev said Uzbekistan planned a second and a third nuclear power plant and tied the plans to its uranium mining. "Our uranium production is growing significantly," he said, according to Gazeta.uz, which reported that talks with new partners and investors on the second plant were scheduled for 17 October. He did not give locations, capacities, timelines or costs, and it was unclear which investors would take part, the outlet said.
The first plant is being built with Russia's state nuclear corporation Rosatom in Forish district of Jizzakh region. It combines two 1,000 MW VVER-1000 units and two 55 MW RITM-200N small reactors, for 2,110 MW in total, and was estimated on 2 September to cost $9.5 billion, Gazeta.uz reported. The first small reactor is scheduled for technical commissioning in 2029 and the first large unit in 2033. The presidential release says a dedicated industrial zone is planned to make equipment and materials for the plant.
Targets for 2030
The government aims to add 22,000 MW of generating capacity by 2030, lift annual electricity output above 129 billion kWh and raise the renewable share to 54 per cent, from 31 per cent of generation now, the release says. The sector has attracted $35 billion of investment over the past decade. Six more solar and wind projects with a combined 2,200 MW are to be put out to tender "in the near future".
Networks are to grow alongside generation. By 2030 Uzbekistan plans to build 5,000 kilometres of power lines and 16 major substations and to raise storage capacity to 4.5 gigawatts, according to the release. A map of available grid connections is due by 1 March next year and a National Energy Master Plan to 2050, the first to be published, by 1 July. Fully prepared projects will be offered through open competitive tenders, with land allocation, grid connection and electricity purchase terms set out in advance. The release also cites the need to secure reliable supply for industrial enterprises and data centres as their demand grows.
An investor council and local manufacturing
Investors at the meeting proposed a permanent mechanism to deal with land allocation, grid connections and technical approvals. In response, an Energy Sector Investors Council will be set up under the head of the Presidential Administration to resolve issues from project preparation to commissioning, the release says. Twelve projects worth a total of $850 million have been prepared to localise production of high-voltage equipment, energy storage systems and wind turbine components, and new mechanisms will let green power producers earn additional revenue from certificates and carbon credits.
On the sidelines of a meeting of the Council of Foreign Investors in the Fuel and Energy Sector the same day, Mirziyoyev received the heads of the Chinese companies CAMCE, China Energy and Sinoma Energy and supported their initiatives to set up a logistics hub in Andijan region, develop agrivoltaics and carry out oil and gas projects, a separate release shows. In oil and gas, exploration is under way on six investment blocks on the Ustyurt plateau with SOCAR and BP, and another 128 blocks have been prepared for potential foreign investors, according to the main release, which also mentions a methanol-to-olefins project in Bukhara region and the modernisation of the Bukhara and Fergana refineries.
Neither presidential release identifies the six signed projects or their sponsors, and no tariffs or financing terms were published. Mirziyoyev first spoke publicly about preparations for a second nuclear plant on 17 August, during a visit to Khorezm region, Gazeta.uz noted, and the authorities have not officially announced a builder for it.