Solidcore Resources' gap between price and all-in sustaining costs (AISC) would narrow from $2,836 to about $2,260 an ounce at the 15 October spot gold price and first-half unit costs, a fall of about a fifth on the Data Desk's calculation.
Solidcore sold gold in the first half of 2026 at an average of $4,748 an ounce, according to its half-year report. Spot gold stood at $4,171.51 on 15 October, Bloomberg reported, about 12 per cent lower on the Data Desk's calculation. Price and volume contributed about equally to the first half's revenue growth, on the Data Desk's decomposition, and only the price component moves with the market.

What the first half rested on
Revenue rose to $972 million from $325 million and adjusted EBITDA to $641 million from $152 million, a margin of 66 per cent, the report shows. It says revenue growth was driven by third-party concentrate processing and the respective sales recovery as well as higher gold prices. Gold-equivalent sales rose to 205 thousand ounces from 104 thousand. Of the $647 million increase in revenue, about $325 million comes from the higher realised price applied to 2026 volumes and about $319 million from higher volumes valued at the 2025 price, on the Data Desk's decomposition, leaving a small rounding residual.
The average LBMA gold price in the half was $4,693 an ounce, up 53 per cent, the report says, against Solidcore's realised $4,748, up 50 per cent from $3,161. AISC fell 13 per cent to $1,912 per gold-equivalent ounce from $2,201. On the Data Desk's arithmetic, the gap between realised price and AISC widened to $2,836 an ounce from $960, almost threefold.
Gold since the half-year
Gold fell by more than 8 per cent in September even as global gold ETFs took in more than 70 tonnes, the World Gold Council said on 5 October. Mining.com, citing the council's data, put the month-end price at $4,176 an ounce, down from $4,563 at the end of August after a 13 per cent gain that month. On 14 October bullion slumped by as much as 1.9 per cent to below $4,090 after US consumer prices jumped the most in five months, Bloomberg reported. It recovered to $4,171.51 the next day.
Spot at $4,171.51 is about 11 per cent below the first-half LBMA average and about 12 per cent below Solidcore's realised price, on the Data Desk's calculation. The level gold fell below on 14 October is about 14 per cent under the realised price.
Sensitivity and the balance sheet
Holding AISC at the first-half $1,912, the gap between price and AISC at three price points works out as follows, on the Data Desk's arithmetic.
- At $4,748, the first-half realised price: $2,836 an ounce.
- At $4,171.51, spot on 15 October: about $2,260, or 20 per cent lower.
- At $4,090, a level gold fell below on 14 October: about $2,178, or 23 per cent lower.
The company kept 2026 guidance of about 540 thousand ounces of gold-equivalent production and AISC of $1,850 to $2,050 per ounce, the report says. Applied to first-half sales of 205 thousand ounces, the $576 lower price would have removed about $118 million of revenue, or 18 per cent of adjusted EBITDA, before any change in mining tax. Each $100 an ounce is worth about $54 million of revenue on the guided volume, if all of it is sold at that price.
The report attributes the rise in mining tax to a new progressive extraction tax and to higher gold prices, and the passage does not say how the tax would respond to a lower price. Tenge appreciation added $73 per ounce to AISC in the report's bridge, and the report says its guidance estimate remains contingent on the tenge-dollar exchange rate. The per-ounce figures above therefore hold every cost at its first-half level.
The report puts cash at $878 million and net cash at $653 million at 30 June, and cash at $1.4 billion and net cash at $747 million at 31 August. First-half free cash flow was $243 million. The $1.2 billion tender offer at $11.66 a share, open from 9 September to 12 October and subject to a general meeting on 30 September, is about five times that free cash flow, on the Data Desk's arithmetic. The company said leverage is "projected to remain below 0.3x Net Debt/Adjusted EBITDA" after the offer. The report, dated 8 September, predates the vote and the close of the offer and does not cover their outcome. Capital expenditure guidance for 2026 is $510 million, including $315 million for the Ertis pressure-oxidation plant, with most of the spending expected in the second half.
On the Data Desk's reading, the cushion remains wide. At the first-half AISC, the gap to price would close only if gold fell about 54 per cent from the 15 October level. How much of the roughly 20 per cent compression in the per-ounce gap reaches EBITDA would depend on how mining tax, the tenge and inflation move.