Qarmet begins main installation at 540,000-tonne rolling mill due by end-2026
The Temirtau steelworks is also building 1.5m tonnes of coke capacity and reprocessing old slimes, while D.A.R. Metall weighs joint projects.
Written with AI tools by Corridor Minerals' editorial system; the publisher is responsible for it. How this site works

The Qarmet steelworks in Temirtau, Karaganda region, has begun installing the main equipment and pipework for a new section rolling complex with capacity of about 540 thousand tonnes of finished products a year, due to be commissioned at the end of 2026, Kursiv reported on 13 October in an article illustrated with company photographs. The mill is one of several projects in a modernisation that the president's office says was discussed with a German metals company in Berlin on 29 September.
The complex will make rebar for housing, infrastructure and industrial construction, including high-strength A600 and A1000 grades used in reinforced concrete for projects with demanding specifications such as nuclear power plants, according to Kursiv. It will take billet through to finished rolled product in a single line. Qarmet's stated strategic aim is to raise steel production to 5 million tonnes a year, the report says.
Work is concentrated inside the main building, where equipment and pipes are being installed and floors, roofing and wall panels laid, while pump and compressor stations, a water treatment plant and electrical rooms are being built alongside, the project manager told the paper. He said the project was on schedule.
A German partner and a state priority
At a meeting in Berlin on 29 September, President Kassym-Jomart Tokayev briefed Christian Artner, chairman of the board of D.A.R. Metall AG, on progress in the reconstruction of Qarmet, which the Akorda statement calls the flagship enterprise of the metallurgical sector. The two sides discussed a joint metal processing project in Kazakhstan, and Artner expressed interest in new projects jointly with Qarmet and in a municipal and industrial waste processing project in Alatau city, according to the president's office. The statement gives no project names, values or dates.
Kursiv, reporting the meeting, set out other parts of the programme. Qarmet plans to finish coke oven batteries No. 8 and No. 9, with combined capacity of 1.5 million tonnes of coke a year, in 2028, and has started refractory brickwork on battery No. 8, which is due to start in November 2027, the paper reported. Once the new batteries reach design output, Qarmet plans to take batteries No. 1 to 4, in service since the 1960s, out of operation in stages. A hot-dip galvanising and polymer coating line and a new flat rolling complex are also being built, Kursiv said.
Ore from old slimes
Upstream, Qarmet has started a concentrator, designated OKV-150, at Karazhal to reprocess iron-bearing slimes accumulated over decades of ore beneficiation, Kursiv reported on 9 October. The plant can handle up to 150 tonnes of feed an hour. At planned rates it is expected to treat about 100 thousand tonnes of slime a month and produce about 30 thousand tonnes of iron ore concentrate grading around 52 per cent iron, or up to 360 thousand tonnes of concentrate a year from up to 1.2 million tonnes of slime, the paper said. The concentrate will go to Qarmet's steel department.
Those figures imply a mass yield of about 30 per cent from slime to concentrate, on Headframe's arithmetic (30 thousand tonnes out of 100 thousand tonnes). The report does not give the iron content of the slime feed, so the iron recovery cannot be calculated. Kursiv also reported that Qarmet's iron ore department is developing new lines, including manganese ore mining.
What the reports do not say
- The cost of the rolling complex, the coke batteries or the slime plant, or how they are financed.
- The supplier of the rolling mill equipment.
- How much rebar Qarmet expects to sell at home and how much to export.
- Whether D.A.R. Metall would take part in any Qarmet project as investor, supplier or customer.
Qarmet has not published these figures in a filing or on its corporate website, and the Kursiv reports carry no separate company statement. The next milestone is commissioning of the rolling complex, which Kursiv puts at the end of 2026.