Kazchrome's Aktobe smelter installs boilers for 80 MW furnace-gas station
The ERG plant expects up to 532 million kWh a year from ferrochrome off-gas once the station is commissioned in 2027; no cost has been published.
Written with AI tools by Corridor Minerals' editorial system; the publisher is responsible for it. How this site works

The Aktobe Ferroalloys Plant in western Kazakhstan, owned by ERG's TNC Kazchrome JSC, has begun installing two high-pressure steam boilers for an 80 MW power station that will run entirely on gas from ferrochrome smelting, a report ERG republished on 6 October 2026 said.

The report, first published by Kursiv on 5 October, gives the station a maximum capacity of 87 MW and planned output of up to 532 million kWh a year. The project turns a smelting by-product into power for the smelter itself. Instead of being disposed of, the furnace gas will be burned to generate electricity for the plant, which will burn more than 80 thousand cubic metres of the gas an hour, the ERG text says. Construction started at the end of 2025 and the station is scheduled to be finished and commissioned in 2027, the report says.
The plant is the older of Kazchrome's two ferroalloy smelters. ERG's page on Kazchrome says it produces more than 700 thousand tonnes of ferroalloys a year and that its smelting shop No. 4, opened in 2014, has four direct-current furnaces rated at 72 MW each, now operating at 75 MW with a prospect of moving to 80 MW. The new station's design capacity is therefore about the size of one of those furnaces, a comparison the company does not make.
What is on site
Work is running on several parts of the station at once, the report says. Besides the two boilers, the main building and turbine hall are going up, along with a gasholder, a cooling tower and an 80-metre chimney, and utility networks and electrical systems are being installed. The boilers, generator, condenser, pumps and other large items have been delivered; the turbine, electrical systems and automation are the next stage.
The plant's main step-down substation, GPP-2, is being rebuilt so that the station can be tied into the works' power system, the report says. Project coordination sits with ERG's energy division and the smelter's own engineers, and the international inspection company Bureau Veritas checks the quality of the main equipment at the manufacturers' works, Kursiv reported. A priority for the coming months is to close the building envelope so that installation and commissioning work can continue through the winter.
Carbon and market access
Kudrat Shamiyev, chief executive of ERG in Kazakhstan, said that the carbon footprint of products was becoming more important alongside quality and price and was now an important condition of access to world markets, and described the station as an example of the group using secondary energy to generate its own power while reducing its environmental impact, the Russian-language report says. Artem Pirozhkov, chief engineer of the project, said the station would become an important part of the plant's energy system once running, Kursiv reported.
The planned output of 532 million kWh a year is equivalent to the station running at about 76 per cent of its 80 MW design capacity across a full year, on Headframe's arithmetic (80 MW multiplied by 8,760 hours gives 700.8 million kWh). That is a high load factor, which fits a station fed by a continuous by-product stream rather than by wind or sun.
What the report does not say
- The capital cost of the station, or how it is financed.
- The name of the EPC contractor, which the report mentions without naming.
- How much of the plant's electricity demand the station will cover, or how much it will cut the plant's purchases from the grid.
- Any estimate of the reduction in carbon dioxide emissions.
The report also does not say whether a similar unit is planned at Kazchrome's larger Aksu plant in Pavlodar region, which ERG's Kazchrome page describes as producing more than 1 million tonnes of products a year. The next milestone named in the report is installation of the turbine, ahead of commissioning in 2027.