Katpar tungsten in Kazakhstan: what is agreed, what is financed, what is still open

Cove Kaz holds 70% of the venture; US agencies have signalled up to $1.6 billion in non-binding financing, and mining is targeted for 2030.

Written with AI tools by Corridor Minerals' editorial system; the publisher is responsible for it. How this site works

Orange scheelite crystals on a pale crystalline rock, against a black background
Scheelite, a tungsten ore, from the Yaogangxian mine in Hunan, China Photo: Géry PARENT, public domain, via Wikimedia Commons, cropped

Cove Kaz Capital Group holds 70 per cent of Severniy Katpar LLP, the Kazakh company that controls the Northern Katpar and Upper Kairakty tungsten deposits in the Karaganda mining district, and the national mining company Tau-Ken Samruk holds the other 30 per cent, according to a company press release of 29 April. The release says the venture owns the largest known undeveloped tungsten resource globally and aims to provide long-term, secure supply to the United States and allied markets. This explainer sets out what has been agreed, what has been financed and what remains open as of mid-October.

What has been agreed

Cove Kaz said it completed the financial closing of the share purchase agreement for its stake on 29 April, and the release does not disclose the price or financing terms. The company cites JORC-compliant resources of 1.4 million tonnes of tungsten trioxide (WO3) from feasibility studies completed in April 2023, a mine life of more than 50 years and anticipated production of about 12,000 tonnes a year, made up of about 5,000 at Northern Katpar and 7,000 at Upper Kairakty. It says that is approximately 15 per cent of current global production, according to the release. Nariman Absametov, chairman of the management board of Tau-Ken Samruk, called the partnership an important step in advancing Kazakhstan's strategic minerals sector.

Cove Kaz will develop, finance, construct and operate the mining and the downstream processing and refining, the release says, including offtake agreements with US government and commercial parties. Mining Technology reported in February that the definitive study work includes refining capacity in Kazakhstan to produce ammonium paratungstate and other tungsten compounds, that the project is expected to create about 2,000 jobs during construction and operation, and that the 1.4 million tonnes equates to about 70 per cent of Kazakhstan's estimated tungsten resources.

On 30 April Cove Kaz and Skyline Builders Group Holding Limited, listed on Nasdaq as KAZR, signed a transaction agreement for a business combination, and the combined company would be named Kaz Resources Inc. and trade under the KAZR ticker, according to a second Cove Kaz release published in July. That release did not say when the combination would close. Metal Tech News reported in October that completion is targeted for the fourth quarter of 2026 or early 2027, subject to required approvals.

Timetable and financing

The July release said site preparation would begin that month at Northern Katpar, covering a first land survey, site roads, initial drill pads and a site office, with core drilling in August in support of a definitive feasibility study. The April release said the definitive study would start in the second half of 2026 and that the 2023 studies would be updated over the next 18 months. Metal Tech News reported that Cove Kaz has engaged DRA Global, ERM and Knight Piésold for the study, that it is scheduled for completion by the end of 2027 and that mining is targeted to begin in 2030.

On financing, Mining Technology reported that the US Export-Import Bank and the US International Development Finance Corporation were offering up to $900 million and $700 million respectively, against projected development costs of about $1.1 billion. Metal Tech News described the amounts as indicative financing interest and potential support, said neither is a finalised funding commitment, and noted that the combined $1.6 billion exceeds the earlier cost estimate. The Times of Central Asia wrote that such letters are preliminary expressions of interest, not final loan approvals, binding commitments or government contracts, and that any financing remains subject to due diligence, agency approvals and other conditions. Neither Cove Kaz release gives financing terms.

Market context and open points

Kazakhstan produced about 2,400 tonnes of tungsten in 2025, according to the Association of Mining and Metallurgical Enterprises, and shipped 3,700 tonnes of tungsten concentrates worth $71 million that year, all to China, the Times of Central Asia reported. The two figures are given as reported and are not reconciled here. The newspaper added that prices rose sharply through 2025 and into 2026 after China imposed export restrictions in February 2025.

Several points remain open: the purchase price, whether the Skyline combination wins its approvals, the outcome of the definitive study, whether the US agencies' interest converts into financing, and which offtake agreements are signed. The resource and production figures date from the 2023 studies and company estimates. The April release describes the deposits as the largest known undeveloped tungsten resource globally in one place and as among the largest in another, so the claim is the company's own and has not been independently verified here.

Sources

Assay notes

  1. Cove Kaz Capital Group completes financial transaction to acquire majority ownership in tungsten joint venture in KazakhstanCove Kaz Capital Group (Business Wire), Primary source, 29 April 2026
  2. Cove Kaz Capital Group begins site preparation at Northern Katpar in support of final drillingCove Kaz Capital Group (Business Wire), Primary source, 9 July 2026
  3. Cove Kaz, Tau-Ken Samruk partner on Kazakhstan tungsten projectMining Technology, Secondary source, 16 February 2026
  4. Skyline merger puts Kazakh tungsten in playMetal Tech News, Secondary source, 14 October 2026
  5. U.S.-Kazakhstan Tungsten Venture Advances as Critical Minerals Cooperation DeepensThe Times of Central Asia, Secondary source, 1 May 2026