Policy and Trade

Kazakhstan's amended uranium subsoil rules take effect on 7 September

Kazatomprom says its licences can pass only to entities in which it holds over 50 per cent, or 75 per cent for ISR, and exploration moves to contracts.

Written with AI tools by Corridor Minerals' editorial system; the publisher is responsible for it. How this site works

Aerial view of drilling rigs and trucks scattered across a flat sandy wellfield under a clear sky
Drilling rigs developing a wellfield at the Inkai uranium mine, Kazakhstan, 2019 Photo: NAC Kazatomprom JSC, CC BY-SA 4.0, via Wikimedia Commons, cropped

Amendments to Kazakhstan's Subsoil Use Code that change how uranium licences are transferred, extended and explored took effect on 7 September, Kazatomprom said in its first-half results release of 21 August.

The page of Kazatomprom announces 1H2026 financial results as published online
The document as published: Kazatomprom announces 1H2026 financial results. Kazatomprom, 21 August 2026.

The company said three laws covering radioactive waste management, energy and the civil nuclear industry, and subsoil activities were signed on 7 July 2026 and amend the Code and other legislation. The release does not assess how the changes affect Kazatomprom.

Licence transfers and extensions

The framework for production licences now depends on the type of deposit, the release says. For open-pit or underground deposits, a uranium licence held by the national operator can be transferred only to a legal entity in which the operator's equity stake exceeds 50 per cent. For in-situ recovery (ISR) deposits the threshold is unchanged at more than 75 per cent. Kazatomprom currently holds the national operator status on uranium. Any other shareholders in a recipient entity would therefore hold less than 50 per cent, or less than 25 per cent for ISR (on Headframe's arithmetic).

On extensions, the release says the authorised regulatory body may decide to extend a uranium production period, but only after the government approves. The extension is conditional on proportionate obligations in the mining contract and in separate agreements, which must relate to national security or to strategic projects of nationwide value for the state. Such projects may be proposed by a foreign shareholder in a uranium mining joint venture, by a foreign government, or by both.

Exploration and radioactive waste

The legal framework for uranium exploration changes from licensing to a contracting regime, under a subsoil use agreement, the release says. Newly issued exploration agreements can be extended once, by up to five years, within a maximum total duration of 11 years. Liquidation work that mining enterprises previously carried out in-house will be done exclusively by the national operator for radioactive waste management, a function the release describes as newly established under the law on radioactive waste management, No. 335-VIII, dated 7 July 2026.

On 25 September the Times of Central Asia, citing a Kazatomprom announcement of 21 September, reported that the company had been granted six-year exploration rights to the Kyzyltu block in Kyzylorda region, with preliminary resources of about 10,000 tonnes. The report does not say whether the rights were granted under the new contracting regime.

Why the thresholds matter

The US Geological Survey says Kazatomprom operated 14 mining assets at 27 sites, of which 2 were wholly owned and 12 partially owned, in its 2024 country data. Kazakhstan produced 23,270 tonnes of uranium in 2024, up 10 per cent, which the same page puts at 39 per cent of world production. It also says amendments made in 2023 to the Subsoil and Use of Subsoil Code were expected to raise the domestic share for exploration and mining operations from 50 per cent to 70 per cent, including uranium, and to tighten control over uranium production. Buyers outside the country depend on that output: Kazakhstan was the origin of 28 per cent of uranium delivered to US reactor owners in 2025, the US Energy Information Administration says, and of 20.31 per cent of EU utilities' natural uranium purchases, the Euratom Supply Agency reports.

The release ties the first-half cost increase to tax, not to the code changes. Attributable C1 cash cost rose 37 per cent and all-in sustaining cost 25 per cent in dollar terms from the first half of 2025, primarily because the mineral extraction tax rate rose from 9 per cent to 12.4 per cent, with higher sulphuric acid costs and a stronger tenge also cited, it says. Kazatomprom raised its 2026 guidance for C1 cash cost to $25.50 to $27.00 a pound from $23.50 to $25.00, and for all-in sustaining cost to $39.00 to $40.50 from $35.00 to $36.50.

The release summarises the three laws and does not reproduce their text. It does not name the joint ventures or partners affected, say how many existing licences meet the thresholds, or set out what obligations a foreign shareholder or government could offer in return for an extension.

Sources

Assay notes

  1. Kazatomprom announces 1H2026 financial resultsKazatomprom, Primary source, 21 August 2026
  2. Kazakhstan Mineral Summary (2024 data), accessed 17 October 2026US Geological Survey, National Minerals Information Center, Primary source, 17 October 2026
  3. Uranium Marketing Annual Report, 2025 dataUS Energy Information Administration, Primary source, 29 July 2026
  4. Market Observatory: EU natural uranium purchases 2025, accessed 17 October 2026Euratom Supply Agency, European Commission, Primary source, 17 October 2026
  5. Kazatomprom secures new uranium block as nuclear demand expandsThe Times of Central Asia, Secondary source, 25 September 2026