Glencore says Kazzinc's own gold output fell 42 per cent on lower grades

Kazzinc's own sourced gold was 237,000 ounces in nine months as grades fell at its ATK mine; third-quarter output was 88,000 ounces against 89,000.

Written with AI tools by Corridor Minerals' editorial system; the publisher is responsible for it. How this site works

Cover card: Kazakhstan gold, Kazzinc's own gold output falls 42 per cent

Kazzinc, Glencore's Kazakh zinc and gold producer, produced 237,000 ounces of gold from its own sources in the first nine months of 2026, 42 per cent less than a year earlier, as head grades fell at the Altyntau-Kokshetau mine, Glencore said on 29 October.

Kazzinc's own gold output by quarterounces
Source: Glencore, Third Quarter 2026 Production Report, 29 October 2026

The third quarter production report puts the shortfall at 171,000 ounces against January to September 2025 and ties it to lower grades at the mine, known as ATK, "as it transitions into its next development phase". The refurbishment of the ATK processing mill that Glencore reported earlier in the year has been completed, with normal operations resumed, the report says.

Glencore controls almost 70 per cent of Kazzinc, and most of the rest belongs to the state mining holding Tau-Ken Samruk, the Kazakh business site Inbusiness.kz reported in July. The 237,000 ounces are the whole of the gold that Glencore's zinc business reports from its own sources.

The third quarter steadied

The quarterly table shows where the drop happened. Kazzinc's own gold output was 127,000 ounces in the third quarter of 2025 and 135,000 ounces in the fourth. It fell to 60,000 ounces in the first quarter of 2026, recovered to 89,000 ounces in the second and was 88,000 ounces in the third, which Glencore's table shows as 1 per cent below the second quarter.

The half-year production report of 29 July gave two reasons for a 47 per cent fall to 149,000 ounces in the first six months: lower head grades at ATK and the refurbishment of one of its two processing mills during the period. With the mill back in service, grade is the only reason the third quarter report gives, and third-quarter output was still about 31 per cent below the 127,000 ounces of the same quarter of 2025, a Newsdesk calculation from the table.

The report gives no gold forecast for Kazzinc and does not say when the next development phase at ATK is expected to lift grades.

Smelters short of outside concentrate

Kazzinc's smelters also treat material bought from other miners, and that side of the business shrank too. Including third-party feed, Kazzinc's smelters produced 469,000 ounces of gold in the nine months, 35 per cent less than the 720,000 ounces of a year earlier. Zinc metal fell 12 per cent to 162,600 tonnes and copper metal 7 per cent to 35,200 tonnes, while lead metal rose 6 per cent to 60,600 tonnes.

Unlike the mine output, total smelter gold fell between the second and third quarters. It was 124,000 ounces in the first quarter, 187,000 ounces in the second and 158,000 ounces in the third, 16 per cent below the second quarter, the table shows. Total smelter silver fell 19 per cent to 5.98 million ounces in the nine months.

Glencore puts the zinc and lead shortfall down to the supply of outside material rather than to its mines. Own sourced zinc production of 142,400 tonnes was 5 per cent lower than a year earlier, and own sourced lead production of 23,200 tonnes 19 per cent lower, "primarily due to limited availability of high-quality third-party concentrates for blending, which reduced the rate at which the smelters could process own sourced material", the report says.

The mix inside the zinc figure moved as a result. Zinc metal from Kazzinc's own sources fell 24 per cent to 68,900 tonnes, while zinc sold in concentrate rose 23 per cent to 73,500 tonnes, so more of the company's own ore left as concentrate instead of being refined. Own sourced silver metal, excluding silver in concentrate, fell 5 per cent to 2.35 million ounces, and own sourced copper metal 4 per cent to 10,700 tonnes.

What it means for Kazakh gold supply

Kazzinc's lower output arrives in a year when the National Bank of Kazakhstan, which has the right to buy all gold produced in the country, bought close to 36 tonnes in the first eight months and then said it would cut gold's share of reserves, as Corridor Minerals reported on 23 October. On the resource side, the government counts 157.2 tonnes of gold added to resources and reserves in 2024 and 2025, a figure that names no deposits or mine lives.

At group level, Glencore kept its full-year 2026 production guidance for its key commodities and said it expects zinc towards the upper end of its range. The report does not break that guidance down by asset.

Sources

Assay notes

  1. Third Quarter 2026 Production ReportGlencore, Primary source, 29 October 2026
  2. Half-Year Production Report 2026Glencore, Primary source, 29 July 2026
  3. Сырьевой гигант Казахстана пережил обвал производства золота (Kazakhstan's commodities giant sees gold output slump)Inbusiness.kz, Secondary source, 29 July 2026