Erdene's Zuun Mod study shows US$745 million NPV for Mongolian moly-copper project

The preliminary assessment assumes US$687 million of initial capex and a 34-year life, but inferred resources make up about 74% of plant feed.

Written with AI tools by Corridor Minerals' editorial system; the publisher is responsible for it. How this site works

Shiny grey flakes of molybdenite on a lump of white quartz
Molybdenite on quartz from the Moly Hill mine in Québec, Canada, 2010 Photo: Didier Descouens, CC BY 3.0, via Wikimedia Commons, cropped

Erdene Resource Development said on 14 October that a preliminary economic assessment of its Zuun Mod molybdenum-copper project in Mongolia returns an after-tax net present value of US$745.1 million at an 8 per cent discount rate and an after-tax internal rate of return of 16.1 per cent, on initial capital expenditure of US$686.8 million, according to the company's release. The Toronto-listed company's base case assumes US$25.00 a pound for molybdenum and US$5.00 a pound for copper, with payback in the sixth year of production.

The page of Erdene announces preliminary economic assessment results for Zuun Mod molybdenum-copper project as published online
The document as published: Erdene announces preliminary economic assessment results for Zuun Mod molybdenum-copper project. Erdene Resource Development Corp., 14 October 2026.

What the study assumes

The release sets out a 34-year mine life with nominal throughput of 25 million tonnes a year and 834.2 million tonnes of total plant feed, at grades of 0.041 per cent molybdenum and 0.058 per cent copper. Average annual recovered production is about 19.8 million pounds of molybdenum and 27.9 million pounds of copper. Over the life of the mine that adds up to 672.1 million pounds of molybdenum (304.9 thousand tonnes) and 947.2 million pounds of copper (429.6 thousand tonnes). The strip ratio is 1.31 to 1.

Initial capital cost includes US$176.7 million of contingency and is spread over a three-year construction period. Sustaining capital is US$462.6 million and closure costs are US$86.5 million, for a total of US$1,235.9 million. The all-in sustaining cost is US$13.89 a pound of molybdenum, with a C1 cash cost of US$10.24, the release says. At the base prices, annual production is worth about US$635 million before any deductions, of which molybdenum accounts for about 78 per cent, on our calculation, matching the share the Northern Miner gives for molybdenum's part of projected revenue.

Spot case and the inferred share

At spot-case prices of US$33.00 a pound for molybdenum and US$6.50 for copper, the study shows an after-tax net present value of US$1,980.7 million, an internal rate of return of 27.8 per cent and payback in the fourth production year. Undiscounted life-of-mine EBITDA is US$7.1 billion in the base case and US$13.0 billion in the spot case.

The resource estimate, effective 1 May 2026 at a cut-off of 0.025 per cent molybdenum, has measured and indicated resources of 407.1 million tonnes at 0.048 per cent molybdenum and 0.062 per cent copper, and inferred resources of 596.2 million tonnes at 0.041 per cent and 0.056 per cent. Inferred material makes up about 74 per cent of the plant feed in the study, and about 16 per cent of feed in the six-year payback period, the release says. It adds that inferred resources are too speculative to be classed as reserves and that the results are less certain than those of a pre-feasibility or feasibility study. Northern Miner quotes Erdene as saying the assessment "doesn't establish economic viability".

Funding and next steps

The release contains no funding plan. It says only that Erdene is in talks with multiple potential partners on offtake, financing and strategic partnership structures. Northern Miner reports that the company is seeking a partner for the larger project while expecting cash flow from gold, and that the Bayan Khundii gold mine, 35 kilometres west of Zuun Mod, has entered commercial production through a 50:50 joint venture with Mongolian Mining. It puts Zuun Mod about 280 kilometres from a railhead at the Mongolia-China border and says shares rose 1.8 per cent to C$5.71 on the day, valuing Erdene at about C$374 million. Northern Miner gives initial capex as C$976 million, so the build cost is about 2.6 times the company's market value, on our division.

Peter Akerley, president and chief executive, said in the release: "This PEA confirms Zuun Mod as one of the world's premier undeveloped resources of molybdenum." Northern Miner quotes him describing the construction cost estimate as "relatively modest for the scale of the project given the economics of operating in Asia", and reports that the company sees production within five years, without giving a calendar year in the body of the article. The release, for its part, gives no start date.

Drilling is due to begin in late October to upgrade and expand the resource and to test for copper across the wider porphyry system, with engineering, environmental and hydrogeological work running alongside. A 2027 programme is meant to convert inferred resources to measured and indicated, starting with the first five years of the mine plan. The technical report is to be filed on SEDAR+ within 45 days of the release.

Sources

Assay notes

  1. Erdene announces preliminary economic assessment results for Zuun Mod molybdenum-copper projectErdene Resource Development Corp., Primary source, 14 October 2026
  2. Erdene eyes 2031 start for $687M Mongolia moly projectThe Northern Miner, Secondary source, 15 October 2026